BIMTECwas appointed by Al Jaber Engineering – Tekfen JV as a BIM Consultant to establish the BIM Department for full Management and Coordination for all stages of the project. BIMTEC also provides Construction and As-Built BIM production including but not limited to construction models, shop drawings and delivery of the integrated Asset Information Model (inclusive of COBie datasheets). Additionally, BIMTEC provides laser scanning survey and technology to be employed for recording As-Built elements and verifying against the construction BIM Models, as well as deviation report point clouds against 3D Models.
QATAR ORBITAL HIGHWAY
JECbuilt Orbital Highway in 2019, Joint venture with Leighton Contracting Qatar. The road infrastructure project—located west and south of Doha city—will provide the New Orbital Highway connecting Mesaieed to Salwa Road. The major elements consist of:
57 km of road works with 5 main interchanges (30 km of 14 lanes Orbital Highway / 27 km of 8–16 lane side roads)
4 no. Grade-separated cloverleaf type interchanges and 1 no. Grade-separated junction comprising 24 no. Bridge structures
18 no’s braiding and emergency exits
Pedestrian & bicycle paths with appropriate underpass structures
New utilities such as surface drainage works, TSE line, electrical works, street-lighting works, Q-Tel, QAF, ITS ducts.
RAS ABU ABOUD STADIUM
BIMTEChave been assigned by HBK Contracting Company, the main contractor of Ras Abu Aboud Stadium and Precinct project to manage and provide solutions to all BIM and Coordination related scope inline with the Supreme Committee (SC) requirements. These requirements include reviewing and auditing the design models deliverable by design consultants, providing coordination and clash detection services between all disciplines, 4D/5D, COBie, tagging assets, and providing As-Built models LOD500 with drawings via the use of laser scanning. BIMTEC also represents HBK for the overall BIM management during the design and construction phases through the BIMTEC on-site management team and provides the shop drawings and LOD400 models for all disciplines through the BIMTEC technical off-site team. Other services include laser scanned surveying, laser scanning technologies employed for recording As-Built elements and verification against BIM construction models, as well as reporting deviation point clouds against 3D Models.
This project to construct 10 interchanges on Salwa International Highway consisted of the following main tasks:
Site clearance and demolition
Earthworks
Sub-base and road base
Flexible surfacing
Road marking
Bridge structure
Street lighting
34 km of cable trench
16 km of water pipelines
The scope also extended to all associated civil, mechanical and electrical works.
QATAR PETROLEUM DISTRICT
Built by JECin 2016, Joint venture with Bouygues and Midmac Contracting. This development involved a building complex in the Qatar Petroleum District, situated in Doha’s new business district in West Bay in a built area covering approximately 700,000 m². The development comprises:
9 high-rise office towers, 52 stories high
Five-star hotel
15 podiums
Elevated state-of-the-art car park for more than 5,000 cars
Primary substation and energy center
The Barwa Financial District is a complex and prestigious project conceptualized to serve the global, regional and local financial sector.
DEAD SEA RESORTS
Developments on 3 separate plots within the Jordan Dead Sea Development Zone; one of which is a four-star hotel and the other is a wellness centre focused on health therapy, employing natural methods to treat skin diseases, respiratory diseases, rheumatic diseases, cardiac diseases, and others.
DOHA METRO GOLDLINE
Built in 2019, Doha Metro is part of the Qatar Integrated Railways Program (QIRP). The Gold Line underground section of the network runs East/West through the heart of Doha City, starting to the East at Airport City and continuing through Al Sharq, Doha Souq, Msheireb and Al Adhawaa, before following both Al Sadd Street and Al Waab Street to the West of Doha and terminating at Sports City in the Aspire Zone. The scope of work will include the design and construction of all civil engineering and building work for this section.
AL AIN HOSPITAL
Al Ain Hospital is a general hospital delivering health services to all Al-Ain patients located at Al Jimi, Al Ain. The project consists of a two-storey hospital building which involves parking facilities, a logistics center, and a 60MW primary substation. The hospital will have 719 beds, including 484 beds for general medicine, surgery section, children’s ward, and maternity; 67 for ICU; 142 for medical rehabilitation; 26 for VIP patients and royal suites.
Out of the 713 beds, 150 beds will be dedicated to rehabilitation. The hospital will also include 104 advanced specialized clinics, 17 radiology rooms for X-ray, computerized tomography (CT) scans, and magnetic resonance imaging (MRI) services, as well as 22 specialized rooms for endoscopy diagnosis and procedures.
QATAR COOL
Built by JECin 2016, the works for this project include the design, supply, delivery, erection and installation on-site of a district cooling plant with a guaranteed capacity of 35,000 tons of mechanical refrigeration and a 5,000 ton thermal energy storage tank (TES) capacity. Work on the plant, which is intended to serve the West Bay area, includes architectural and civil works together with the provision of all the necessary mechanical, electrical, plumbing and fire (MEPF) equipment and installations, as well as the associated structures, and the civil works of Kahramaa substation.
BIMTEC provides laser scanning survey for constructed elements, records As-Built elements and verifies against BIM construction Models. BIMTEC also provides deviation report point clouds against 3D Model of primary structure and MEP. Every part of the stadium district has been designed with sustainability in mind. After the 2022 FIFA World Cup Qatar™ has elapsed, almost half of the stadium’s 40,000 modular seats will be removed and given to football development projects abroad. The smaller post-tournament arena will enable Al Rayyan to maintain the intimate, neighbourly character it is famous for.
AL RAYYAN STADIUM WORK
COLLEGE OF ENGINEERING
The College of Engineering, established in 1980, has become one of the largest colleges in Qatar University and is providing the community and industry with high-quality professional engineers who have excelled in their practice and showed commitment in their leadership positions due to by the innovative education they receive.
ALJABER ENGINEERING HEAD OFFICE
JEC is a leading general contractor based in the State of Qatar. Established in 1995 as part of Al Jaber Group a major conglomerate with over 40 companies JEC has successfully completed numerous large-scale turnkey projects for many prestigious clients in various sectors. The company’s commitment to executing top quality projects, on schedule and within budget while adhering to the highest health, safety and environmental standards has earned JEC iconic status in the construction community in Qatar. We have attained numerous international qualifications for our Integrated Management System (IMS) initiatives and continually strive to implement and achieve the latest ISO Certifications. In order to participate more fully in building Qatar’s infrastructure as well as meeting the growing demand for a range of new developments, JEC has expanded its resources by recruiting new staff with international experience as well as investing heavily to upgrade its fleet of equipment.
BIMTEC was appointed by ALJABER TECHINCAL AND TRADING (JTC) for the production of a LOD300 model based on the current MEP design for structure and Architecture, and As-Built models (LOD 500) of the same design. BIMTEC’s scope also includes 4/5D extractions and the production of Construction stage COBie exchange files (and validation of them), as per Construction Stage and As-Built COBie deliverable standards.
FANAR ISLAMIC CULTURAL CENTER
Completed in 2005 by JTC, A center dedicated to the Islamic culture that consists of a basement, ground floor and eight floors which works comprises construction completion and maintenance with complete building setup from infrastructure and external works with electrical works installation, mechanical, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings.
HAMMAD PORT VISITOR CENTER
HAMMAD PORT VISITOR CENTER
The Port Visitor center building is located outside the Port security fence but within the Port Administration Area, and will be easily accessed by port employees and visitors. The purpose of the building is to provide information to Port visitors, as well as accommodation for educational activities related to port operations, port construction and history studies of maritime activities in Qatar. BIMTEC was appointed by JTC for the production of a LOD300 model based on the current MEP design for structure and Architecture, and As-Built models (LOD 500) of the same design. BIMTEC’s scope also includes 4/5D extractions and the production of Construction stage COBie exchange files (and validation of them), as per Construction Stage and As-Built COBie deliverable standards.
SOUTH MARINA YACHT CLUB
Built by JTC in 2016, the design and build services shall include without being limited to: a) Architecture – Architectural Design – Façade Engineering Design b) Civil and infrastructure engineering Design c) Structural Engineering Design d) MEP and utilities Engineering Design e) Interior Design f) Geotechnical engineering g) Topographical Survey h) Environmental and sustainability engineering, able to develop GSAS strategy i) Fire safety engineering j) Lighting Design k) Acoustic Design l) Security Engineering m) Vertical transportation Engineering n) IT engineering o) Audio Visual Engineering p) Quantity Surveying q) Project Management and scheduling (r) GSAS sustainability study (s) BIM Services
SOMERSET APARTMENT WESTBAY
Built by JTC in 2019, The Scope of Works in this contract comprises, but is not limited to, the following:
-General Description of the Work A. Replacement of building facade (curtain wall, cladding & louvre) and main entrance canopy B. Addition and alteration to existing MEP system C. Addition and alteration to existing apartments guestroom floors D. Addition and alteration to roof, basement, ground and first floors E. All necessary interfacing works between construction phases and the existing buildings/structures and MEP system F. Works at areas not listed above (or out w~h phasing) shall follow requirements listed under Works Outside Works Area.
RADISSON BLU HOTEL
Built by JTC in 2007, Construction completion and maintenance of a new ten-story hotel building with complete building setup from infrastructure and external works which includes roads and landscaping to building construction, electrical works installation, plumbing, internal works, structural, architectural and mechanical works as described in the project specifications, contract documents and drawings.
BEVERLY HILLS TOWER
Built By JTC, Prepared in 2006, Construction completion and maintenance of a tower that consists of a basement, ground floor, first floor, club house, 26 floors and two penthouse floors along with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural and architectural works as indicated in the drawings & project specifications.
CENTURY MARINA HOTEL
Built by JEFFERSON in 2022, Set in Lusail, 3.7 km from Lagoona Mall, Century Marina Hotel – Lusail offers accommodation with an outdoor swimming pool, free private parking, a fitness center and a restaurant. Each accommodation at the 5-star hotel has city views, and guests can enjoy access to a sauna and a hot tub. The accommodation provides a 24-hour front desk, airport transfers, room service and free WiFi.
HAMMAD AQUATIC CENTER
Built By JTC in 2006, Construction completion, commissioning and maintenance of a major aquatic center which includes complete building setup from infrastructure and external works to electrical works installation, plumbing, internal works, structural and architectural works as described in the project specifications, contract documents and drawings.
ACS DOHA INTERNATIONAL SCHOOL
Built by JTC in 2020, The Project is to deliver a purpose designed premium 2,470 student school to continue to best serve the needs of our Doha community. ACS Doha International School Al Kheesa Campus is proposed to have a total floor area of roughly 27,000m2, delivering education to students from pre-school to pre-university, with an age range of three years old until the age of 18. Approximately floor area 28,000m2.
DOHA AIRPORT LANDSCAPING
Built By JTC in 2014, Bicycle Path: • Construction of 5m. wide combined pedestrian/bicycle path with an approximate length of 10 km. • Site installations and traffic diversions • Levelling works and earthworks • Granular sub-base • Asphalt works, painting and imprinting • Kerbing works and interlocking, tiling, paving • Traffic signs, road markings • Solar reflective studs
Bus Shelters: • Construction of 10 air-conditioned Passenger Bus Shelters • Structural foundation including the surround slab • Steel structural frame • Shelter shade canopy • Air-conditioned toughened laminated glazed shelter waiting room • Remote air-conditioning in trench pit • Internal seating • Demarcated baggage area • Internal & External lighting • Zone identification marking & banner • Utility cabling through existing ducts and source connections
Parking Shades: • Construction of single and double cantilever shade structures containing 1 and 2 LED lighting units Ras Abu Abboud Road Interchange and Drainage Compound Landscaping: • Soft Landscaping Works • Hardscaping • Irrigation Network • Electrical and Lighting Works
INTERNATIONAL SCHOOL OF CHOUEIFAT
Built by JTC in 2004, Reinforced concrete building including MEPD associated works with complete building setup from infrastructure and external works which includes roads and landscaping to building construction, internal works, structural and architectural works as described in the project specifications, contract documents and drawings.
QATAR FINANCIAL CENTER
Built By JTC, QFC aims to promote Qatar as a major business and commercial hub at the crossroads between East and West.We invite businesses, from start-ups to large corporations seeking to expand to the region, to benefit from flexible legal and regulatory services, regulated and non-regulated, that meet international best practice. With QFC, you can accelerate business growth in Qatar and beyond, while becoming part of Qatar’s swift expansion into a major trade and investment hub.
AL SULAITI TOWERS
Built by JTC in 2004, An office building consisting of a basement, ground floor + 15 floors with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural, architectural and all electro-mechanical works as indicated in the drawings & project specifications.
BARWA COMMERCIAL AVENUE
Built By JTC in 2008,
Enabling works of Barwa Commercial Avenue comprise the following: Site clearance, removal of debris and dumped material from the commercial strip and disposal to approved tip offsite
Bulk backfilling works to raised plot platform between 0.5 to 0.75m above existing road level.
Main site offices
Hoarding for the entire site
Advertising sign boards
QREIC
Built by JTC in 2008, Construction completion & maintenance of 2B + G + M + 14 floors—Qatar Real Estate Investment Company office building along with all services and other MEPD associated works and infrastructure facilities with external works to building construction, structural and architectural works as indicated in the drawings & project specifications.
AL SHAMAL HEALTHCARE CENTER
Built By JTC, Al Shamal Health Center is located in Abu Dhalouf, Qatar, and is part of the Primary Health Care Corporation (PHCC).The center has units for family medicine, pediatrics, dental clinic, ophtalmology, mental health, laboratory, pharmacy, ultrasound and radiology, among others.PHCC manages more than 20 health centers throughout Qatar, looking for giving specialized medical care according to the needs of each area.Al Shamal Health Center has EN-54 certified public address and voice evacuation systems made by LDA Audio Tech in its facilities.
QATAR WOMEN CLUB SPORTS HALL
Built by JTC in 2005, Concrete structure building covered by steel and an aluminum dome that provides a range of different sports facilities and spa exclusively for women.
Qetaifan Island North
Scope of Works is in three parts, one each for each Package and comprise the following: Linear Park Canal • Formation of the canal by excavation down to bed level (-2.5m QNHD). Canal Edges • Soil reinforced marine wall Abra Stations • 3 No. Abra stations including pontoons, gangways, piles, and services as specified. Bridges (Road bridges and foot bridges) • Construction of the abutments of 3 No. road bridges excluding the decks •Construction of 3 No. foot bridges with concrete abutments and steel beam deck construction. Piling works • Preliminary earthworks for the piling area including filling and compaction, these include the formation of a piling platform in the sea. Total Number of Piles – 2717 Nos Canal crossings • Construction of 2 No. temporary canal crossings and handover to the Employer (Package 4). Miscellaneous • Aids to navigation including beacons at the entrances, piled daymarks at the Mangrove island, and buoys in the dredge channel.
BIN AL SHEIKH TOWERS
Built by JTC in 2021,
The works comprise the design, construction and commissioning of the Bin Al Sheikh Towers, 91,697.80m2 Built Up Area. The Works shall include all construction and fit-out elements required for a fully functional and fit for purpose Apartment Building including but not limited to: • All architectural fit-out works including, interior finishes, Millworks and the like • Civil / Structural works • Lifts and Escalators • Building envelope and façade • Building Maintenance Unit (BMU) • Roofing Systems and Skylight Domes • Mechanical works / air-conditioning and ventilation • HV, LV & ELV Electrical supply and distribution • Earthing and Lightning Protection • Voice and Data Installations • Access Control systems • Security and Surveillance systems installation (CCTV) • Guest Room management systems • Lighting & special lighting fixtures • Potable water supply • Plumbing Works • Toilet & Bathroom installations • External & Internal walls and partitions • External & Internal Doors and Window